Results

1076 - 1100 of 1414 Items    << < 39 40 41 42 43 44 45 46 47 48 > >> 
Thumbnail
Title
Description
Dates
Spillway section of the dam as seen from the left bank near the shop building. Note the man and care at the waterline. (normal)
1942-04-28
Construction of the Pumping Plant Structure, Grand Coulee Dam, Coulee Dam, Washington. Installation of pumping unit P-2 discharge pipe, showing reinforcing steel being placed in concrete form is the square opening of the block out which extends...
1949-05-16
Progress photos of the East Powerhouse as of date.
1941-08-07
Progress view of the stage of construction on the R-1 scroll case.
1948-08-17
View of all of the spillway arches.
1941-07-31
View of the spillway section of Grand Coulee taken from the right bank.
1941-05-05
Riveting and welding face plates on drum gate #1
1941-01-28
Steel and Form work for drum gate installation. Steel is for spillway crest, bridge piers, and drum gate chamber
1940-06-20
South Coulee Dam--Main Canal Headowrks--View taken from the east bank of the approach channel looking west and downstream. Mixer and ""Pumperete"" set-up are shown in the central part of the view. The cut-off wall footing which runs through the...
1948-05-04
A tight fit. The clearance between the huge 25-foot rotors and the stators of the two 75,000 kilowatt Shasta Dam generators, being installed at Grand Coulee Dam to make additional power available for war industries, is only 5/8 inch. Lowering this...
1942-11-28
Col. Basin Proj., Grand Coulee Dam.--Rotor for main generator unit L-6 in the west powerhouse at Grand Coulee Dam being carried to final position by two overhead travelling cranes using an equalizing beam. The rotor, 31 feet in diameter, weighing...
1943-06-08
Chinook migrants in dividing box near the end of Dryden Ditch
1940-07-14
Bolts and nuts weighing 193 pounds, couple the sections of the shafts for the two 75,000 kilowatt Shasta generators being installed in the Grand Coulee Dam left powerhouse. The bolts are five inches in diameter and 25 inches long. Each section of...
1942-12-29
Placing scroll case section L1 W. powerhouse
1941-08-21
Close up view of a man gauging offsets between concrete units
1938-02-01
Due to lack of proper transportation equipment, difficulty was encountered in taking the R-1 rotor shaft across the spillway roadway of the dam. In order to distribute the load safely, it was necessary for this truck boom to hook onto the trailer...
1948-07-21
concrete specimens-not yet submerged in water for testing
1938-08-19
Photograph is a side angle of a topographical map where the dam will be built.
1941-10-16
Specifications No. 2475, March 24, 1949. This photograph was taken as the floating caisson was being submerged in the spillway bucket during its initial trial operation. The caisson barge with operating equipment is shown floating between the...
1949-03-24
Showing granite armor rock along the left riverbank below Grand Coulee Dam ready for placing in section ""A."" The rock is obtained from the upriver quarry. This work is performed by J.A. Terteling and Sons, Inc., under provisions of negotiated...
1949-04-26
View of cracked and bent terminal stud on top of Westinghouse 230-kv bushing serial No. 3 for 36,000-kva transformers purchased under specifications No. 1025
1947-07-30
Birdseye view of Cedar Creek falls and small power developement

Burner at the completed Tucannon weir near Starbuck, Washington
1937-11-30
2003-01-01
1 map: blueprint ; 51 x 48 cm. In 1901, Mr Ben F. Ross, an employee of the Great Northern Railroad, settled with his family in the area that became the town of Omak, Washington. By 1906, Ross had helped to organize the first...
2024-04-29

1076 - 1100 of 1414 Items    << < 39 40 41 42 43 44 45 46 47 48 > >> 

© Western Waters Digital Library - GWLA member projects - Designed by the J. Willard Marriott Library - Hosted by Oregon State University Libraries and Press