Title | Summary of the Central Arizona Project and Power Considerations |
Description | Document: Summary of the Central Arizona Project and Power Considerations, November 8, 1966 (thermofax), page 2 -2- 3. Off-and On-Peak Power Pumping In general, if the CAP is built to accommodate off-peak pumping, you need 1 mill per KWH savings in power cost to equal the added investment in the project in tunnels and pumps. 4. CAP Power Costs At 61/2 mills, it is $12 million annually; At 4 mills, it is $7,400,000 annually; At 21/2 mills, it is $4,600,000 annually. 5. Bureau Power Studies Presently Carried on in Phoenix Set out below are the different situations the Bureau is... Epson Perfection 4870 Photo, 400 dpi, 24 bit, 1,705,931 bytes |
Creator | Unknown |
Date | 1966-11-08 2006-9-26; 2006-09-28 |
Type | text |
Format | image/jpeg |
Identifier | su04942.jpg http://server16127.contentdm.oclc.org/u?/udallcoloradoAZU,14589 |
Source | Az 372 Box 169, Folder 4 |
Language | eng |