Title | Summary Report - Central Arizona Project with Federal Prepayment Power Arrangements |
Description |
Summary Report, Central Arizona Project with Federal Prepayment Power Arrangements, February 1967, map
SUMMARY SHEETS
COSTS
Project Costs
Granite Reef Aqueduct $ 336,430,000
Salt-Gila Aqueduct 38,400,000
Tucson Aqueduct 42,030,000
Orme Dam & Reservoir 38,418,000
Buttes Dam & Reservoir 31,974,000
Charleston Dam & Reservoir 33,048,000
Hooker Dam & Reservoir 28,797,000
Drainage System 10,500,000
Power Generation and Transmission Arrangements 91,950,000 |