Title | Summary Report - Central Arizona Project with Federal Prepayment Power Arrangements |
Description |
Report: "Summary Report Central Arizona Project With Federal Prepayments Power Arrangement", February 1967, page 26
Interest During Construction (3-1/8 percent)
Aqueduct system $40,462,000
Power generation and transmission arrangements 5,087,000
Water salvage and recovery 1,444,000
Total $46,993,000
Annual equivalent cost (100 years, 3-1/8 percent interest) $1,539,000
Annual Operation, Maintenance, and Replacement
Aqueduct system $3,203,000 |