Title Page 2
Type text
Format image/jpeg
Identifier su00333.jpg http://server16127.contentdm.oclc.org/u?/udallcoloradoAZU,5122
Description Assuming F. Y. 1963 Supplemental Funds are available by April 15, 1963, and other funds available as needed, the proposed schedule of construction for Phase 1 and 2 is as follows: F. Y. 1963 Salinity Control Works Flood Control Works Phase 1 * $2,000,000 F. Y. 1964 Phase 1 * 4,000,000 " 2 1,500,000 4,500,000 F. Y. 1965 Phase 2 2,000,000 7,500,000 F. Y. 1966 Phase 2 4,000,000 6,000,000 F. Y. 1967 Phase 2 1,500,000 3,000,000 * Represents $6,000,000 Supplemental request... Epson Perfection 4870 Photo, 400 dpi, 8 bit, 955,772 bytes