Description D. Project Costs As shown on the attached Table 4, the cost of initial construction for the Snake-Colorado Project would be $945.7 million and the cost of the deferred expansion program $346.8 million, for a total construction cost of $1.293 billion. The overall cost, including $104.9 million for interest during construction, would be $1.397 billion. A summary of all annual costs for the Snake-Colorado Project is shown on the attached Table 5. The annual capital cost of $44.2 million per... Epson Perfection 4870 Photo, 400 dpi, 8 bit, 16,312,320 bytes