Eleven-inch pipe line transporting cement from storage silos to mixing plant - 7,000 feet long, using 100 lbs. air pressure.
1936-06-01
2024-11-25 |
Concrete mixing plant on west side. Placing trestle at right.
1936-06-01
2024-11-25 |
Filling and discharge ends of the four concrete mixers in Eastmix.
1936-06-01
2024-11-25 |
Batcher control equipment in Eastmix. Graphic record instrument on the right.
1936-06-01
2024-11-25 |
North end of block 40 in foreground, timber crib plug to cofferdam cell cluster, center tower of aggregate suspension bridge tower in cell 5, cofferdam section "G"; Bridge spans on both sides of tower, 1437 feet. Elevation, top of tower 1280,...
1936-01-01
2024-11-25 |
Bedrock and concrete blocks in west area; low trestle, and conveyor bridge to Westmix on the right; high trestle on the left.
1936-01-30
2024-11-25 |
Winter conditions at foot of concrete placing trestle support.
1936-02-01
2024-11-25 |
Blocks in dam near bedrock, looking west from block 30 - low placing trestle in upper right.
1936-03-03
2024-11-25 |
Behind section "E" of west cofferdam, showing work on block 40 and wood plug to cells in section "G";
1936-03-03
2024-11-25 |
The two placing trestles and forms for concrete. Colby and Clyde-Wiley cranes handling the four-yard buckets. Upper right shows aggregate conveyor suspension bridge running to west mixer.
1936-03-24
2024-11-25 |
Carload of 4-yard concrete buckets on 950 elevation trestle.
1936-05-26
2024-11-25 |
One of three Krane-Kars setting a form in dam. Capacity, 5,000 pounds with 12-ft. boom to 2,500 pounds at 18-ft. boom 55 horsepower gasoline engine.
1936-04-01
2024-11-25 |
Downstream section in west powerhouse showing reinforcing in base under draft tubes.
1936-04-30
2024-11-25 |
Typical forms in dam. Reinforcing steel in longitudinal gallery walls.
1936-05-01
2024-11-25 |
Vibrating concrete in east training wall, using Jackson 2-man machines operating at 4,800 r.p.m. 145 volts.
1936-05-19